FirmGreen, Inc.  

Company News

FirmGreen's Biogas Project in Brazil Nears Completion

For first time visitors to this page, the slideshow automatically plays; you can also navigate by using the numbered tabs or the arrow buttons.
For those who have viewed earlier slides, newer images start at slide #10, which you can manually select by clicking the numbered tab.


  • Surveying the Site in Brazil

    Novo Gramacho Landfill: Brazil

    Steve Wilburn, CEO of FirmGreen, Inc. stands atop the Novo Gramacho landfill, pointing toward the nearby Petrobras facility that will use cleaned biogas from the landfill as fuel.

    FirmGreen's equipment is arriving at a site located adjacent the landfill, where it will be assembled to process the landfill's biogas so that it becomes clean biomethane fuel, with an energy content equivalent to natural gas.

  • Aerial View

    Aerial View of the Project

    At the top of the photo, you can see Novo Gramacho the landfill depicted in the Wasteland movie. This large landfill is the source of the biogas that will be cleaned using FirmGreen's green technology, currently being installed at Gás Verde's biogas purification plant.

    The yellow line represents the route of the pipeline that will transport cleaned gas to a nearby customer in this case, Petrobras.

  • Pipeline

    The Pipeline is Underway

    The illustrations at right depict the process of boring beneath road & the waterway along the pipeline route visible in the previous image.

    Constructing the pipeline that will deliver cleaned biomethane fuel is all a part of the project, which will help improve air quality at the landfill while making beneficial use of its waste gas to provide power for a nearby business operation.

  • Substation

    Construction is Well Underway

    The building visible at left in this photo will house an electrical substation at the Gás Verde biogas purification facility.

    Other structures (shown in right photo) at the site will soon house other equipment that is part of the biogas processing operation.

  • Equipment in Transit

    Equipment Arrives

    FirmGreen's equipment traveled from Ohio to Texas, then by cargo ship to the port of Rio De Janeiro.

    After arrival & inspection at Port Rio, the equipment was loaded onto trucks for the last leg of the journey to the Gás Verde facility, located at the Novo Gramacho landfill.

    As it arrives, the team in Brazil is ready to install and assemble the biogas purification equipment that will produce biomethane. The cleaned biogas will then be transported by pipeline (slide #2) to help operate the Petrobras plant just "down the hill".

  • Unloading Crew

    Safely On The Ground

    The Gás Verde site in Brazil has been under construction while the equipment was fabricated in the USA, and is ready for equipment installation.

    The crew in Brazil is making sure each skid of the biogas purification equipment is offloaded safely and installed in the proper location.  

  • Concrete Pads at Processing Plant

    Equipment Installation

    In October, concrete pads stood empty, awaiting unloading of the remaining equipment.

    The equipment visible in this photos are compressor coolers — part of the biogas processing plant that will produce pipeline quality natural gas from dirty landfill methane.

  • Processing Plant

    Installation Progress

    By mid-December, significant progress on construction of the biogas facility is visible.

    Most of the equipment has now arrived at the site of the biogas processing plant and is being carefully assembled and installed.

    The tall, cylindrical components beyond the workers, to the right, are "purge vessels" that filter impurities out of the biogas.

  • Substation Progress

    Substation Progress

    The small inset image shows the electrical substation construction progress as of late October 2011.

    Visible in the large photo is the same structure as of mid-December. Still under black wraps inside the building are power transformers.

  • Birds Eye View at Processing Plant

    Bird's eye view of site

    Early December: visible in the foreground of the photo is the frame for the structure that will house electrical cabling being routed from the substation to biogas processing plant.

    Beyond the electrical structure, the biogas purification equipment is being mounted on the concrete pads.

  • Biogas Processing Plant Takes Shape

    The plant is taking shape!

    Late January 2012, progress on the biogas processing plant is visible.

    After some inclement weather delays, workers are back on the site installing extensive piping that is all part of the facility's operation.

  • Workers Install Piping at Processing Plant

    Plant installation progresses

    Late January 2012, a closer view of the workers atop the steel framework, as they continue to install pipes that are part of the biogas processing plant.

    Below the steel framework, the biogas purification equipment and containment vessels are visible.

  • Biogas Processing Plant early 2012

    Above & ground level views

    In the background of the left photo, taken late January 2012, is the structure and workers seen closeup on the previous slide.

    Beyond the containment vessels at mid-photo, another module of the biogas processing equipment has been installed.

    In the right side photo, taken below the electrical structure, other workers are doing the many welds to connect piping from biogas containment vessels to the pipeline that will carry cleaned biogas.

  • Bird's Eye View: February

    Bird's Eye View: February

    As construction continues under sunnier skies, the biogas cleaning facility is a hub of activity.

    The large trucks seen along the road carry dirt away from the trench being dug for the gas pipeline that will carry cleaned biogas to the customer.

    (see slides #2 and 3 for more pipeline info)

  • Locals visit

    Local road hazards...

    Some local livestock have arrived to check out roadside conditions at the plant, undoubtedly looking for any edible debris.

    While they don't seem to have gotten the hardhat memo, they're not blocking the road, so delivery of equipment from the staging area to construction continues without any interference.

  • Ohio workers load FirmGreen equipment

    Last Shipment Ready to Go

    On the ground in Ohio, workers load the last pieces of equipment.

    This 4th and final shipment of FirmGreen technology is headed to the port of Jacksonville, Florida and then on to Brazil.

  • Equipment install in Brazil

    On the Ground in Brazil

    Brazilian workers continue to install the biogas processing equipment as it arrives.

    The 4th and final shipment arrived late May, and the plant is expected to be up and running late 2012.

  • Global FirmGreen Energy

    View More Photos!

    We've posted more photos of the recent facility progress. Click to View

    Read more about this project
    Read the recent project update
    Read recent news about Ex-Im Loan
    View "Starting Point: Ohio" slideshow

    Find out more about FirmGreen's
    gCNG® — a natural gas fuel from renewable sources, an energy source that is environmentally sound ready today!
    Read More


What is my environmental impact?
Check your carbon footprint here
  Quick Links
  Company News
  Careers
   
Back To Top

Connect with us:

Find FirmGreen on Facebook Follow FirmGreen on Twitter FirmGreen YouTube channel
spacer
  Copyright © 2003 - 2014 FirmGreen, Inc.® | All Rights Reserved