FirmGreen's Biogas Project is Underway in Brazil



  • Surveying the Site in Brazil

    Novo Gramacho Landfill: Brazil

    Steve Wilburn, CEO of FirmGreen, Inc. stands atop the Novo Gramacho landfill, pointing toward the nearby Petrobras facility that will use cleaned biogas from the landfill as fuel.

    FirmGreen's equipment is arriving at a site located adjacent the landfill, where it will be assembled to process the landfill's biogas so that it becomes clean biomethane fuel, with an energy content equivalent to natural gas.

  • Aerial View

    Aerial View of the Project

    At the top of the photo, you can see Novo Gramacho — the landfill depicted in the Wasteland movie. This large landfill is the source of the biogas that will be cleaned using FirmGreen's green technology, currently being installed at Gás Verde's biogas purification plant.

    The yellow line represents the route of the pipeline that will transport cleaned gas to a nearby customer — in this case, Petrobras.

  • Pipeline

    The Pipeline is Underway

    The illustrations at right depict the process of boring beneath road & the waterway along the pipeline route visible in the previous image.

    Constructing the pipeline that will deliver cleaned biomethane fuel is all a part of the project, which will help improve air quality at the landfill while making beneficial use of its waste gas to provide power for a nearby business operation.

  • Substation

    Construction is Well Underway

    The building visible at left in this photo will house an electrical substation at the Gás Verde biogas purification facility.

    Other structures (shown in right photo) at the site will soon house other equipment that is part of the biogas processing operation.

  • Equipment in Transit

    Equipment Arrives

    FirmGreen's equipment has traveled from Dublin, Ohio to Houston, Texas, then by cargo ship to the port of Rio De Janeiro.

    After arrival in Port Rio, the equipment was inspected and then loaded onto trucks for the last leg of the journey to the Gás Verde facility, located at the Novo Gramacho landfill.

    As it arrives, the team in Brazil is ready to install and assemble the biogas purification equipment that will produce biomethane. The cleaned biogas will then be transported by pipeline (shown in slide #2) to help operate the Petrobras plant just "down the hill".

  • Unloading Crew

    Safely On The Ground

    The Gás Verde site in Brazil has been under construction while the equipment was fabricated in the USA, and is ready for equipment installation.

    The crew in Brazil is making sure each skid of the biogas purification equipment is offloaded safely and installed in the proper location.  

  • Concrete Pads at Processing Plant

    Equipment Installation

    In October, concrete pads stood empty, awaiting unloading of the remaining equipment.

    The equipment visible in this photos are compressor coolers — part of the biogas processing plant that will produce pipeline quality natural gas from dirty landfill methane.

  • Processing Plant

    Installation Progress

    By mid-December, significant progress on construction of the biogas facility is visible.

    Most of the equipment has now arrived at the site of the biogas processing plant and is being carefully assembled and installed.

    The tall, cylindrical components beyond the workers, to the right, are "purge vessels" that filter impurities out of the biogas.

  • Substation Progress

    Substation Progress

    The small inset image shows the electrical substation construction progress as of late October 2011.

    Visible in the large photo is the same structure as of mid-December. Still under black wraps inside the building are power transformers.

  • Birds Eye View at Processing Plant

    Bird's eye view of site

    VIsible in the foreground of the photo is the frame for the structure that will house electrical cabling being routed from the substation to biogas processing plant.

    Beyond the electrical structure, the biogas purification equipment is being mounted on the concrete pads.

  • Global FirmGreen Energy

    Check Back Soon!

    We will post more photos as the facility assembly progresses and becomes operational, so check back for updates.

    Read more about this project
    View "Starting Point: Ohio" slideshow

    Find out more about natural gas (methane) fuel, and what's different about renewable vs. traditional methane fuels. Find out why FirmGreen's gCNG® — natural gas from renewable sources, is environmentally sound energy.
    Read More



Read the Related Article    View "Starting Point: Ohio" Slideshow    Back To Press Index
What is my environmental impact?
Check your carbon footprint here
  Quick Links
  Company News
  Careers
   
Back To Top
Find FirmGreen on FacebookFollow FirmGreen on TwitterAdd to Favorites
spacer
  Copyright © 2003 - 2012 FirmGreen, Inc.® | All Rights Reserved